This document has 310 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Bid Package 26A - Early Works Electrical
Page 2 Content Index
Page 3 Section 00020 Instructions to Bidders
Page 9 Bid Form
Page 13 Exhibit A Scope of Work / Supply and Clarifications / Qualifications
Page 19 Exhibit B Drawings, Specifications, Addenda and Reference Documents
Page 20 Exhibit C Alternates, Unit Prices, and Labor Rates
Page 25 Exhibit D Project Schedule / Milestones
Page 26 Project Schedule
Page 55 Exhibit E Standard Subcontract Terms and Conditions
Page 74 Exhibit F Supplier Code of Conduct
Page 83 Exhibit G Standard Insurance Requirements
Page 94 Exhibit H Interim Estimate for Payment, Waiver and Release
Page 96 Exhibit I Final Estimate for Payment, Unconditional Waiver and Release
Page 99 Exhibit J Standard Subcontractor Environmental Health and Safety Requirements
Page 103 Exhibit K Standard Change Order
Page 105 Exhibit M Project Specific Requirements
Page 119 Exhibit N Supplemental Terms and Conditions for Subcontract
Page 127 Exhibit O Performance Bond
Page 129 Exhibit O Payment Bond
Page 131 Exhibit PS-1 Owner Contract
Page 132 AIA Document A133-2019 Standard Form of Agreement Between Owner and Construction Manager as Constructor
Page 171 AIA Document A133-2019 Exhibit A Guaranteed Maximum Price Amendment
Page 175 Exhibit B Cost Responsibility Matrix
Page 178 AIA Document A201-2017 General Conditions of the Contract for Construction
Page 255 Exhibit PS-2 Environmental Health and Safety Plan Updates
Page 256 Exhibit Q Standard Environmental Insurance Requirements
Page 258 Exhibit R Quality Management Program
Page 262 Exhibit S Authorized Signatories
Page 263 Exhibit T1 Supplier Diversity Program Summary
Page 265 Exhibit T2 Instructions to Bidders
Page 266 Exhibit T3 Diverse Business Status Verification
Page 269 Exhibit U Sub-Subcontractor Identification
Page 271 Exhibit X Site Requirements
Page 284 Exhibit X.1 Site and Demolition Logistics Plan
Page 293 Exhibit X.2 Paving Plan
Page 295 Exhibit X.3 Temp Power and Lighting
Page 299 Exhibit X.4 Temp Heat Plan (Under Separate Cover)
Page 300 Exhibit X.5 Temp Garage Door Plan
Page 304 Exhibit X.6 Delivery Request Form
Page 306 Exhibit X.7 PlanIt for Construction Work Plan Development