Highline School District - Pacific Middle School Replacement: MACC I Bid Packages, Des Moines, WA - Bid Package 31A - Earthwork & Utilities    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 317 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Bid Package 31A - Earthwork & Utilities
Page 2 Content Index
Page 3 Section 00020 Instructions to Bidders
Page 9 Bid Form
Page 15 Exhibit A Scope of Work / Supply and Clarifications / Qualifications
Page 26 Exhibit B Drawings, Specifications, Addenda and Reference Documents
Page 27 Exhibit C Alternates, Unit Prices, and Labor Rates
Page 32 Exhibit D Project Schedule / Milestones
Page 33 Project Schedule
Page 62 Exhibit E Standard Subcontract Terms and Conditions
Page 81 Exhibit F Supplier Code of Conduct
Page 90 Exhibit G Standard Insurance Requirements
Page 101 Exhibit H Interim Estimate for Payment, Waiver and Release
Page 103 Exhibit I Final Estimate for Payment, Unconditional Waiver and Release
Page 106 Exhibit J Standard Subcontractor Environmental Health and Safety Requirements
Page 110 Exhibit K Standard Change Order
Page 112 Exhibit M Project Specific Requirements
Page 126 Exhibit N Supplemental Terms and Conditions for Subcontract
Page 134 Exhibit O Performance Bond
Page 136 Exhibit O Payment Bond
Page 138 Exhibit PS-1 Owner Contract
Page 139 AIA Document A133-2019 Standard Form of Agreement Between Owner and Construction Manager as Constructor
Page 178 AIA Document A133-2019 Exhibit A Guaranteed Maximum Price Amendment
Page 182 Exhibit B Cost Responsibility Matrix
Page 185 AIA Document A201-2017 General Conditions of the Contract for Construction
Page 262 Exhibit PS-2 Environmental Health and Safety Plan Updates
Page 263 Exhibit Q Standard Environmental Insurance Requirements
Page 265 Exhibit R Quality Management Program
Page 269 Exhibit S Authorized Signatories
Page 270 Exhibit T1 Supplier Diversity Program Summary
Page 272 Exhibit T2 Instructions to Bidders
Page 273 Exhibit T3 Diverse Business Status Verification
Page 276 Exhibit U Sub-Subcontractor Identification
Page 278 Exhibit X Site Requirements
Page 291 Exhibit X.1 Site and Demolition Logistics Plan
Page 300 Exhibit X.2 Paving Plan
Page 302 Exhibit X.3 Temp Power and Lighting
Page 306 Exhibit X.4 Temp Heat Plan (Under Separate Cover)
Page 307 Exhibit X.5 Temp Garage Door Plan
Page 311 Exhibit X.6 Delivery Request Form
Page 313 Exhibit X.7 PlanIt for Construction Work Plan Development