Page 1 Cover Page
Page 2 Content Index
Page 3 Section 00020 Instructions to Bidders
Page 9 Bid Form
Page 11 Exhibit A Scope of Work / Supply & Clarifications / Qualifications
Page 15 Exhibit B Drawings & Sketches, Specifications, Addenda & Other Documents
Page 18 Exhibit C Alternates, Unit Prices & Labor Rates
Page 23 Exhibit E Standard Subcontract Terms & Conditions
Page 42 Exhibit F Supplier Code of Conduct
Page 47 Exhibit G Standard Insurance Requirements
Page 53 Certificate of Liability Insurance
Page 58 Exhibit H Interim Estimate for Payment, Waiver & Release
Page 60 Exhibit I Final Estimate for Payment, Unconditional Waiver & Release
Page 63 Exhibit J Standard Subcontractor Environmental Health & Safety Requirements
Page 67 Exhibit K Standard Change Order
Page 69 Exhibit M Project Specific Requirements
Page 82 Exhibit N Supplemental Terms & Conditions to Subcontract for Use in the State of Washington
Page 90 Exhibit O Performance Bond
Page 92 Payment Bond
Page 94 Exhibit PS-1 WNER / Contractor Agreement
Page 95 AIA Document A133-2019 Standard Form of Agreement Between Owner & Contractor as Constructor
Page 127 AIA Document A201-2017 General Conditions of the Contract for Construction
Page 191 Exhibit 2 Cost Responsibility Matrix
Page 206 Exhibit PS-2 Environmental Health & Safety Plan Updates
Page 207 Exhibit Q Standard Environmental Insurance Requirements
Page 209 Exhibit R Project Specific Quality Management
Page 213 Exhibit S Authorized Signatories
Page 214 Exhibit T1 Supplier Diversity Program Summary
Page 216 Exhibit T-2 Prime Subcontractor's Initial DB Participation Plan & Monthly Utilization Report
Page 217 Exhibit T-3 Diverse Business Status Verification
Page 220 Exhibit U Sub-Subcontractor Identification
Page 222 Exhibit X Site Requirements & Logistics
Page 227 Exhibit X.1 Early Work Site Logistics Plan
Page 228 Exhibit X-2 Environmental, Health & Safety Manual