Renton High School Replacement - MACC 01, Renton, WA - Bid Package 31A - Earthwork & Utilities    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 160 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 2 Content Index
Page 3 Section 00020 Instructions to Bidders
Page 9 Bid Form
Page 14 Exhibit A Scope of Work / Supply & Clarifications / Qualifications
Page 21 Exhibit A.1 Construction Coordination Process
Page 29 Exhibit A.2 Scope Allocation Drawings (Under Separate Cover)
Page 30 Exhibit B Drawings & Sketches, Specifications, Addenda & Other Documents
Page 36 Exhibit C Alternates, Unit Prices & Labor Rates
Page 41 Exhibit D Project Schedule / Milestones
Page 43 Exhibit E Standard Subcontract Terms & Conditions
Page 62 Exhibit F Supplier Code of Conduct
Page 71 Exhibit G Standard Insurance Requirements
Page 82 Exhibit H Interim Estimate for Payment, Waiver & Release
Page 84 Exhibit I Final Estimate for Payment, Unconditional Waiver & Release
Page 87 Exhibit J Standard Subcontractor Environmental Health & Safety Requirements
Page 91 Exhibit K Standard Change Order
Page 93 Exhibit M Project Specific Requirements
Page 99 Exhibit N Supplemental Terms & Conditions to Subcontract for Use in the State of Washington
Page 107 Exhibit O Performance Bond
Page 109 Payment Bond
Page 111 Exhibit Q Standard Environmental Insurance Requirements
Page 113 Exhibit R Quality Management Program
Page 118 Exhibit S Authorized Signatories
Page 119 Exhibit T1 Subcontractor Engagement Program Summary
Page 122 Exhibit T-2 Prime Subcontractor's Initial & Monthly Diverse Business (DB) Participation Plan
Page 123 Exhibit T-3 Diverse Business Verification Form
Page 125 Map
Page 126 Exhibit U Sub-Subcontractor Identification
Page 127 Exhibit X Site Requirements & Logistics
Page 138 Exhibit X.2 Procore Daily Reports
Page 139 Procore Web-Based Daily Reporting
Page 142 Exhibit X-03 PlanIt for Construction Work Plan Development
Page 146 Exhibit X.4 Delivery Request Form
Page 147 Renton High School Replacement Training Document
Page 153 Exhibit Y Supplemental Terms & Conditions for Subcontractors / Sellers with Design Responsibility
Page 156 Exhibit PS-01 Owner / Contractor Agreement
Page 157 Exhibit PS-02 Environment, Health & Safety Manual
Page 158 Exhibit PS-03 Delineation of Onsite & Offsite Work
Page 159 Exhibit PS-04 Owner Flow Down Provisions