Project #FOR41          Bid Date: 6/17/2025 @ 2:00 pm PDT

Port Angeles Middle School Modernization and Addition - BP 14.00 Hydraulic Elevator, Port Angeles, WA

BP 14.00 Hydraulic Elevator Documents:
Invitation to Bid
Bid Manual
Exhibit A.1 - Site Logistics Plan
Exhibit A.2 - Project Phasing Plans
Exhibit A.3 - Building Dewatering Plans
Exhibit A.4 - S101C Gym Civil Plan with Footing Depths
Exhibit B - Drawing Log
Exhibit C - Specification Log
Exhibit D.1 - BP 31.00 Project Schedule
Exhibit D.2 - Full Project Schedule
Exhibit E - FORMA Standard Subcontract Terms & Conditions
Exhibit E.1 - FORMA Master Subcontract Agreement
Exhibit E.2 - FORMA Master Purchase Order
Exhibit E.3 - FORMA P&P Bond
Exhibit E.4 - FORMA Retention Bond
Exhibit E.5 - Subcontractor Inclusion Plan Template
Exhibit E.6 - Subcontractor Apprenticeship Utilization
Exhibit F - A133-2019 Owner / Construction Manager Agreement
90% CD Structural Concrete / Elevator Bid Set Plans Volume 1
90% CD Structural Concrete / Elevator Bid Set Plans Volume 1 - Survey Plans
90% CD Structural Concrete / Elevator Bid Set Plans Volume 2
90% CD Structural Concrete / Elevator Bid Set Specs
90% CD Structural Concrete / Elevator Bid Set Specs - Owner Provided Ex. Plans

Addenda:
Addendum #1
Addendum #1 Plans
Addendum #2
Addendum #3
Addendum #3 Plans
Addendum #4
Addendum #5
Addendum #6

Register on this project.

View self registered Bidders List

Builders Exchange of Washington, Inc. Subs and Suppliers

GC/CM:
FORMA Construction
1016 1st Ave S, Suite 400
Seattle, WA 98134
206-626-0256
Fax: 360-943-5868

Contact: Mike Johnson
360-480-8922
mikej@formacc.com

Prebid: Site Walk: 5/8 @ 10:00 am at the project location

Description:
The Port Angeles Middle School Modernization and Addition is the modernization of the existing 23,200SF gym building and a new ground up 84,7263SF 3- story middle school. Once the modernization and additions are complete the existing classroom building and portables will be abated and demolished followed by extensive site improvements. Upgrades and New Construction Include:

Existing Gym
• Extensive seismic upgrades
• New MEP systems and equipment
• New roofing, new athletic bleachers, and upgraded interior athletic spaces/offices & finishes

New Classroom Building
• Learning spaces, admin offices, commons, MEP service rooms, music, library, and kitchen
• Extensive exterior canopy structure

Site
• Significant site clearing, earth movement, utilities, and site upgrades including bio-retention ponds
• New service yard, parking, bus loop, outdoor learning areas, and commons/entry plazas
• ROW work at North Alley and D street

This work will occur during summer months and the school year(s) while the existing classroom building is fully occupied until the new classroom building is complete as well as phased occupancy of the existing gym and site.