Project #CRN23          Bid Date: 5/14/2015 @ 3:00 pm PDT

Sunny Hills Elementary School, Issaquah School District, Sammamish, WA #191402

Conformed Documents:
Conformed Plans
Conformed Plans - Additional Plans
Conformed Specs Volume 1
Conformed Specs Volume 2
Revision III Civil Grading Plans Transmittal
Revision III Civil Grading Plans
Revision IV Civil Grading Plans Transmittal
Revision IV Civil Grading Plans
Revision V Civil Grading Plan Transmittal
Revision V Civil Grading Plan
Revision VI Civil Grading Plans Transmittal
Revision VI Civil Grading Plans

ASI's:
ASI #001
ASI #001 Plans
ASI #002 Waterproofing at Foundation
ASI #003 Column Locations
ASI #003 Plans
ASI #004 Temporary Parking Lot Layout
ASI #004 Plan
ASI #005 Elevator Shaft Modifications
ASI #005 Plans
ASI #005 HydroFit Plans
ASI #006 Room 189 Slab Height Revision
ASI #007 Spec Modification Outlets
ASI #008 Hardware Revisions
ASI #008 Plans
ASI #009 Play Shed Option
ASI #009 Plan
ASI #010 Duct in Activity Areas
ASI #010 Plans
ASI #011 Color Schedule Revisions
ASI #012 Room Layout Changes and Casework Additions
ASI #013 Wall Grills at Staff Lounge 213
ASI #014 Mechanical Louver Locations at Mezzanine
ASI #014 Plan
ASI #015 Data Layout and Camera Locations
ASI #015 Plans
ASI #016 Corridor 125 Modification Ceiling Height
ASI #017 Submittal 102 Casework Modifications
ASI #017 Submittal 102 Casework Modifications - Updated Information
ASI #018 Therapy Swing in OT-PT 106
ASI #019 Updated E1.1 Vaults
ASI #019 Plan
AR28 5-A7.11 Entry Vestibule - Room 200 Revised 4/29/16

RFI's:
RFI #001 Grid Line Clarification Confirmation - Response
RFI #001 Plan
RFI #002 Footing Clarification Confirmation - PSM Response (6-18-2015)
RFI #002 Plan
RFI #003 Joist and Beam Location Clarification
RFI #003 Plans
RFI #004 UG Chilled HDPE Pipe Insulation - Hultz Response
RFI #005 Service Yard Screen Wall Revision Confirmation
RFI #006 Grid Line Dimension Discrepancy Clarification - Revised
RFI #006 Plans - Revised
RFI #007 Electrical Site Work
RFI #008 Anchor Bolt Type Confirmation
RFI #009 Footing Elevation Change Confirmation
RFI #010 Joist Bearing Correction Confirmation
RFI #010 Plans
RFI #011 Music Room Sound Rack Coordination
RFI #012 CIP Wall Along GL B.9 Location Confirmation
RFI #013 BF Gusset Plate Weld Correction
RFI #014 Steel Primer Confirmation
RFI #016 Zone B SOMD Penetration
RFI #017 Door 186 Size - Response
RFI #017 Supplemental Email
RFI #018 Door 173 Size - Response
RFI #020 Elevation at Service Yard - Loading Dock
RFI #021 Wall to Pandeck Topplate Connections - PSM Response - Resized
RFI #022 Braced Frame 10.5, H.5 - K.5 - PSM Response
RFI #023 Casework Clarifications - Response - Resized
RFI #024 Beam Hanger Size Revision - PSM Response
RFI #025 Drinking Fountain Orientation - Response
RFI #027 Pad Mount Switch Response
RFI #028 Stage Column - PSM Response
RFI #028 Plan
RFI #033 Door 122B
RFI #033 Plan
RFI #034 High Roof Structural Framing Over Mezzanine
RFI #035 Roof Hatch Location in Room 274A
RFI #036 Shear Wall Connection
RFI #037 Concrete Stair Railing Embedment
RFI #038 Vehicle Traffic Gate
RFI #039 Monument Sign
RFI #041 HDU2/HDU5 Connections - Revised
RFI #042 Mechanical Louver Locations
RFI #042 Plans
RFI #043 Mezzanine Floor Span at Elevator - PSM Response - Revision 1
Modified 10/S4.13 GLB to PSL Connection at Roof Valley
RFI #044 Playshed Structure Steel Elevations
RFI #044 Plan
RFI #048 Fire Smoke Damper and Chase in Storage Room 172
RFI #049 Fixture Type RL Finishes & Shielding
RFI #050 Vaults for Future Portables
RFI #051 Fixture Type X-1 & X-1G
RFI #052 Fixture Type PL2, LT2, & X-1G
RFI #056 Structural Architectural Main Entry Details Above 2nd Floor
RFI #057 Shear Wall Penetrations for Electrical Outlets
RFI #058 Fixture Type WL3-4
RFI #059 Haiku Fan 0-10V Control
RFI #061 Electrical Pipe Runs - Activity Areas Adjacent to Exterior Stairs
RFI #062 Fixture Type RL-8 Kurtzon Lighting
RFI #063 Shear Wall GL E / 10.5-11 - PSM Response
RFI #064 Roof Drain Location
RFI #066 Genothen Casework Question #12
RFI #067 Shear Wall Framing Clarifications - PSM Response
RFI #067 Plans
RFI #068 MSK-6 Creates Louver Clash
RFI #069 Ductwork Conflict in Room 261
RFI #070 HVAC EF-179
RFI #071 Condensate Clarification
RFI #072 Gym Wall Grille
RFI #072 Plans
RFI #073 Shower P-9A Response
RFI #074 CCTV Lot Pole Hand Hole
RFI #074 Plan
RFI #075 Rooftop Boiler Flue Above Room 190 Response
RFI #075 Plan
RFI #076 Lighting Control Device Finish Clarification Response
RFI #079 IDF Room 249B - HVAC
RFI #080 P-5A Sinks
RFI #082 Operable Partition Wall Dimensions
RFI #084 Casework Question #13
RFI #085 WF-3 Panels - Restrooms
RFI #086 Casework Question 15 Cornerguards
RFI #087 Sound Attenuators
RFI #088 Trim at Common Mullion
RFI #090 Casework Question 19 - Room 170
RFI #091 Casework Question 20 - Caulking Decorative Panels
RFI #092 Casework Question 21 - Climbing Wall Finishes
RFI #093 Casework Question 22 - Room 170 Trim / WF-2 Details
RFI #094 Steel Gate Clarification - PSM Response
RFI #095 Casework Question 23 - Rooms 240, 260 Sink Countertop Dimensions
RFI #096 DDC Controls for EH-201 - Response
RFI #098 Casework Room 203 - Decorative Panel
RFI #100 Casework Question 25 - Rooms 171, 181 Plam Color
RFI #101 Room Finishes Rooms 217, 221, 256
RFI #102 Design Review - System Airflow Discrepancies
RFI #103 Wall Louver Conflict with Exterior Entry Soffit
RFI #103 Plan
RFI #104 Zone C Mezzanine Louver Response
RFI #104 Plan
RFI #109 Location of Monument Sign / Readerboard Response
RFI #110 Piper Oven Electrical Requirements - 2
RFI #112 Access Control to Waiting Room 203

CCD's:
CCD #001 Over Excavation and Backfill
CCD #002 Added Rockery on North Side
CCD #003 Bar Joist Beam Seats
CCD #004 Storm Drainage Modification Along 235th
CCD #005 Paddle Fan Change - Haiku-L
CCD #006 Provide CW Domestic Line to Future Portables
CCD #007 For Pricing Purposes Only - Not Direction to Proceed
CCD #008 Wicket Door
CCD #009 Cancelled
CCD #010 Change Portable Water Lines to Plastic
CCD #011 Canceled
CCD #012 Lighting Layout Changes - Revised
CCD #012 Plans - Revised
CCD #013 Power Layout Modifications - Revised
CCD #013 Plans - Revised
CCD #014 AV System Changes
CCD #014 Plans
Revised E4.21 Transmittal
Revised E4.21 Plan
CCD #015 Fire Alarm & Security System Changes
CCD #015 Plans
CCD #016 Air Barrier Substitution - Revised
CCD #017 Paddle Fan
CCD #018 Miscellaneous Framing Revisions
CCD #019 Room 213 Ductwork Revision
CCD #021 Health 205 Refrigerator Modification
CCD #022 Exterior Stair Details
CCD #023 Safety Room
CCD #023 Safety Room - Revised
CCD #024 AHU Bases
CCD #025 Modify Performance Platform Lighting
CCD #025 Plan
CCD #027 Phase 2 Grading Modifications
CCD #027 Plan
CCD #027 Additional Plans
CCD #028 Modify Exterior Stair Railings
CCD #029 Benches at Exterior Stairs
CCD #029 Plan
CCD #030 Site Plan Changes
CCD #030 Plans
CCD #031 Water Service at Portables
CCD #031 Plans
CCD #032 Relocated Street Lights
CCD #033 Modifications to Doors 105 & 175A
CCD #034 ROW Modifications
CCD #035 PIM Interface Modules and Licenses
CCD #036 Power for Ovens in Kitchen
CCD #037 Modifications to Existing Water Main
CCD #037 Plans
CCD #038 Additional Striping
CCD #039 Parking Lot Benches and Baseball Field Gate

Meeting Minutes:
Subcontractor Meeting Minutes 4/5/16

Schedule:
Schedule 4/4/16

Proposal Requests:
COR #001 Epoxy Paint Mezz Floor, Pricing Purposes Only Not Direction to Proceed

Bid Set Documents (Not for Construction Use):

Bid Set Plans - (Not for Construction Use)
Bid Set Specs Volume 1 - (Not for Construction Use)
Bid Set Specs Volume 2 - (Not for Construction Use)
Bid Set Addendum #1 - (Not for Construction Use)
Bid Set Addendum #2 - (Not for Construction Use)
Bid Set Addendum #3 - (Not for Construction Use)
Bid Set Addendum #3 Plan - (Not for Construction Use)
Bid Set Addendum #4 - (Not for Construction Use)

Register as a Bidding Subcontractor and be notified of new docs on this project.

Builders Exchange of Washington, Inc. Subs and Suppliers

Bids to:
Cornerstone General Contractors, Inc
11807 North Creek Parkway S. Ste. 102
Bothell, WA 98011
425-481-7460
Fax: 425-481-7497

Contact: Dave Flynn
dave@cornerstonegci.com

Description:
The project includes construction of an approximately 80,000 square foot two-story building and two covered play structures on a 12.6 acre site including all related site work, off-site street improvements and demolition of existing 42,000 square foot one-story buildings.