Edmonds-Woodway HS Multipurpose Fieldhouse Project, Edmonds School District, Edmonds, WA #24-06CP - Plans
G10 Cover Sheet
G11 Sheet Index
CS01 Project Information & Code Analysis
CS10 Building Area Analysis
SD1.01 Architectural Site Plan
Sheet 1 Boundary & Limited Topographic Survey
Sheet 2 Boundary & Limited Topographic Survey
C0.00 Cover Sheet
C0.01 Overall Site Plan
C1.00 Demolition Plan
C1.01 Demolition Plan
C2.00 TESC Plan
C2.01 TESC Plan
C2.10 TESC Details
C3.00 Grading Plan
C3.20 Grading Sections
C4.00 Storm Drainage Plan
C4.10 Storm Drainage Details
C4.11 Storm Drainage Details
C4.12 Storm Drainage Details
C4.13 Storm Drainage Details
C4.14 Storm Drainage Details
C4.20 Storm Profiles
C5.00 Utility Plan
C5.01 Utility Plan
C5.10 Utility Details
C5.11 Utility Details
C5.20 Utility Profiles
C6.00 Paving & Horizontal Control Plan
C6.01 Paving & Horizontal Control Plan
C6.10 Paving Details
C6.11 Fencing Details
C7.00 Fire Plan
A0.00 General Notes, Symbols & Abbreviations
A1.00 Wall Types
A1.10 Floor Plan - Level 1
A1.11 Floor Plan - Mechanical Attic
A1.41 Roof Plan
A1.51 RCP - Level 1
A2.10 Exterior Elevations
A2.11 Exterior Elevations
A3.10 Building Sections
A3.11 Perspective Views
A3.20 Wall Sections
A3.21 Wall Sections
A4.10 Enlarged Plans & Elevations - Restrooms
A5.11 Floor Finish Plan - Level 1
A6.10 Interior Elevations
A6.11 Interior Elevations
A6.12 Interior Elevations
A7.10 Door Legends & Schedule
A7.20 Opening Details
A7.21 Opening Details
A7.22 Opening Details
A7.30 Glazing Assembly Legends & Schedules
A8.10 Exterior Details
A8.11 Exterior Details
A8.20 Exterior Wall Details
A8.30 Roof Details
A8.31 Roof Details
A9.00 Interior Wall Details
A9.10 Interior Details
A9.11 Interior Details
A9.20 Floor & Ceiling Details
A10.00 Signage
A10.01 Signage
A10.02 Signage
BE000 Notes & Specifications
BE001 Specifications Continued
BE002 Material Location Diagrams
BE100 Below Grade Details
BE101 Below Grade Details
BE102 Below Grade Details
BE103 Below Grade Details
BE200 Wall Details
BE300 Penetration Details
BE500 Window & Door Details
BE501 Window & Door Details
BE502 Window & Door Details
BE600 Roof Details
BE601 Roof Details
BE602 Roof Details
BE700 Air Barrier Semi-Exterior Details
BE800 Air Barrier Notes
BE801 Air Barrier Diagrams
BE900 Notes & Specifications
BE901 Building Envelope Energy Forms
BE902 Building Envelope Energy Forms
BE903 Building Envelope Energy Forms
S0.01 General Structural Notes
S0.02 General Structural Notes
S0.03 General Structural Notes
S0.04 General Structural Notes
S0.05 Special Inspection Schedule
S0.06 Special Inspection Schedule
S0.07 Special Inspection Schedule
S0.08 Symbols & Abbreviations
S2.01 Foundation Plan
S2.02 Mezzanine & Roof Framing Plan
S5.01 Typical Concrete Details
S5.02 Typical Concrete Details
S5.03 Foundation Details
S5.04 Foundation Details
S5.31 Metal Deck Details
S5.60 Wood Shear Wall Schedule & Details
S5.61 Holdown Schedule & Details
S5.62 Typical Wood Framing Details
S5.63 Wood & Steel Framing Details
S5.64 Wood Framing Details
S5.65 Roof Framing Details
S5.66 Roof Framing Details
S5.67 Framing Details
M0.01 Mechanical Legend
M0.02 Mechanical General Notes
M0.03 Mechanical Schedules
M0.04 Mechanical Schedules
M0.05 Mechanical Schedules
M0.06 Mechanical Schedule
MS1.01 Mechanical Site Plan
M1.01 Underground Plumbing Plan
M2.01 Level 1 Plumbing Plan
M2.02 Attic Plumbing Plan
M3.01 Level 1 HVAC Plan
M3.02 Attic HVAC Plan
M5.01 Level 1 Fire Protection Plan
M5.02 Attic Fire Protection Plan
M6.01 Mechanical Roof Plan
M7.01 Mechanical Enlarged Plan
M9.01 Mechanical Details
M9.02 Mechanical Details
M9.03 Mechanical Details
M9.04 Mechanical Details
M9.05 Mechanical Details
M9.06 Mechanical Details
M10.01 Mechanical Controls
M10.02 Mechanical Controls
M10.03 Mechanical Controls
M10.04 Mechanical Controls
M10.05 Mechanical Controls
M10.06 Mechanical Controls
E1.00 Legend
E1.01 Site Plan - Electrical
E1.03 Details
E1.04 Details
E1.05 Details
E2.10 Floor Plan - Level 1 - Lighting
E2.11 Floor Plan - Level 2 - Lighting
E3.10 Floor Plan - Level 1 - Power
E3.11 Floor Plan - Level 2 - Power
E3.41 Roof Plan - Electrical
E4.10 Floor Plan - Level 1 - Communications
E4.11 Penthouse Level Floor Plan - Communications
E5.10 Floor Plan - Level 1 - ESS
E5.11 Penthouse Level Floor Plan - ESS
E6.00 One-Line Diagram, Communications Block Diagram
E7.00 Schedules
E8.00 Schedules
E8.01 Schedules
Order Prints
Drawing List
FastBid 3 Help
FastBid 3 Help
When using the measuring tool, be sure to
verify the set scale
with a known distance such as a dimension or a door.
FastBid requires JavaScript to run. Please call 425-258-1303 for more information.