Pipeline Relocation at Alger Interchange Project, Skagit County PUD, Skagit County, WA #14017 - Specs    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 314 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 2 Section 000105 Certification Page
Page 3 Section 000110 Table of Contents
Page 6 Section 001113 Invitation to Bid
Page 8 Section 002113 Instructions to Bidders
Page 18 Mandatory Bidder Responsibility Checklist
Page 19 Subcontractor Responsibility Checklist
Page 20 Certification of Compliance with Wage Payment Statutes
Page 21 Section 004000 Procurement Forms & Supplements
Page 22 Bidder's Checklist
Page 23 Bid to Commission
Page 24 Bid Schedule
Page 26 Proposal Signature, Addendum Acknowledgement & Non-Collusion Declaration
Page 27 Subcontractors List - RCW 39.30.060 Form
Page 29 Statement of Bidder's Qualifications - Comparable Contract History
Page 30 Bidder's List
Page 31 Bid Bond
Page 32 Section 005200 Agreement Forms
Page 33 Contract
Page 35 Indemnification Agreement
Page 36 Certificate of Owner's Attorney
Page 37 Performance & Payment Bond
Page 39 Section 007200 General Conditions
Page 41 Section 007300 Supplementary Conditions
Page 48 Division 1 General Requirements
Page 49 Section 011100 Summary of Work
Page 51 Section 012200 Measurement & Payment
Page 61 Section 013119 Project Meetings
Page 65 Section 013200 Construction Progress Documentation
Page 69 Section 013300 Submittal Procedures
Page 75 Contractor's Submittal Transmittal Form
Page 76 Section 013529 Health, Safety & Emergency Response Procedures
Page 78 Section 014100 Regulatory Requirements
Page 82 Owner Release Form
Page 84 Section 014213 Abbreviations & Acronyms
Page 86 Section 014219 Reference Standards
Page 88 Section 014500 Quality Control
Page 90 Section 015526.1 Traffic Control
Page 98 Attachment A Contractor's Daily Report of Traffic Control
Page 100 Section 015526.2 Contractor's Daily Report of Traffic Control - Traffic Control Log
Page 101 Contractor's Daily Report of Traffic Control - Summary
Page 102 Section 015719 Temporary Environmental Controls
Page 105 Section 016600 Product Storage & Handling Requirements
Page 107 Section 017113 Mobilization
Page 108 Section 017133.11 Protection of Adjacent Utilities
Page 111 Section 017700 Closeout Procedures
Page 113 Division 31 Earthwork
Page 114 Section 311000 Site Clearing
Page 116 Section 312300 Excavation & Fill
Page 126 Section 312319 Dewatering
Page 130 Section 312500 Erosion & Sedimentation Control
Page 139 Division 32 Exterior Improvement
Page 140 Section 320130 Operation & Maintenance of Site Improvements
Page 142 Section 321123 Aggregate Base & Asphalt Paving
Page 146 Section 321540 Crushed Stone Surfacing
Page 148 Division 33 Utilities
Page 149 Section 330505 Buried Pipe Installation
Page 156 Section 330509.24 Casing Utility Pipe
Page 158 Section 330531.13 Ductile Iron Pipe
Page 163 Section 330533.23 Polyethylene Pipe
Page 170 Section 331413 Public Water Utility Distribution Piping
Page 173 Section 331419 Valves & Hydrants for Water Utility Service
Page 179 Section 331419.12 Butterfly Valves
Page 181 Section 338129 Communication Vaults, Pedestals & Enclosures
Page 183 Appendix A Permits
Page 220 Appendix B Geotechnical Data Report & WSDOT Boring Log
Page 312 Appendix C Inadvertent Discovery Plan