Project #PYS26          Bid Date: 5/6/2025 @ 1:00 pm PDT

Rogers High School Roof Repair Project, Puyallup School District, Puyallup, WA #51-02-25

$613,900

Low Bid:
Bids Received: 4
Apparent Low BidStreamline General Construction LLC$ 898,384.00
2ndNeeley Construction Company$ 933,000.00
3rdCDK Construction Services, Inc.$ 1,118,000.00

Plans
Specs
Addendum #1
Addendum #2
Addendum #2 Plans
Bid Tabulation

Register on this project.

View self registered Bidders List

Builders Exchange of Washington, Inc. Subs and Suppliers

Owner:
Puyallup School District No. 3
323 12th Street NW
Puyallup, WA 98371

Contact: Mike McCanna
D 253-841 8643
M 253-324-2808
MccanMC@puyallupsd.org

Issued by:
www.bxwa.com

Prebid: 4/24 @ 3:30 pm at Rogers High School, 12801 86th Ave E, Puyallup, WA 98375

Description:
The scope of the project includes repair of the existing roof/eave condition and sunshade re-construction at Rogers High School. The scope shall include but not limited too; site supervision, temporary fencing, material hoisting, demolition of existing eaves, Glu-Lam Beams, sunshades, selective demolition of existing roof systems, installation of new rough carpentry fascia, structural supports, Glu-Lam Beams, roof systems, metal flashings, roof drainage and new finishes. Repairs, demolition and re-construction to the existing sunshades are included in the scope and further defined in the bid documents.