This document has 831 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 2 Seals Page
Page 4 Advertisement for Bid
Page 8 Table of Contents
Page 11 Invitation to Bid
Page 15 Instructions to Bidders
Page 33 Bidder Compliance Form
Page 34 Bid Form
Page 36 MWBE, WA Small Business, Veteran-Owned Business Utilization Certification
Page 37 Subcontractor Utilization List
Page 39 Bid Bond Requirements
Page 40 Supplemental Bidder Responsibility Criteria with Inclusion Plan & Apprenticeship Requirements
Page 42 Form 1 Contractor Experience Detail
Page 43 Form 2 Resume of Key Personnel
Page 45 Form 3 Prime Contractor Diverse Business Inclusion Plan
Page 47 Form 4 Apprenticeship Utilization
Page 48 Form 5 Reference Evaluation Questionnaire
Page 49 Form 6 Supplemental Responsibility Criteria Evaluation Score Sheet
Page 50 Summary of Pay Items & Quantities
Page 55 General Conditions for Construction at Washington State Parks
Page 98 Prevailing Wages
Page 99 Section 010000 General Requirements
Page 103 Project Sign Detail
Page 105 Section 010099 Construction Surveying
Page 115 Section 012300 Alternates
Page 117 Section 013300 Submittal Procedures
Page 121 Section 013501 Inadvertent Discoveries of Cultural Resource & Human Skeletal Remains
Page 122 Section 014000 Quality Requirements
Page 130 Section 014100 Regulatory Requirements
Page 134 Section 014200 References
Page 137 Section 015000 Temporary Facilities & Controls
Page 144 Section 015639 Temporary Tree & Plant Protection
Page 151 Section 015719 Environmental Controls
Page 160 Section 016000 Product Requirements
Page 163 Section 017419 Construction Waste Management & Disposal
Page 164 Section 017700 Closeout Procedures
Page 168 Section 024100 Demolition
Page 175 Section 030000 Concrete
Page 191 Section 055050 Galvanizing
Page 195 Section 054100 Structural Aluminum Framing
Page 204 Section 055000 Miscellaneous Metals
Page 216 Section 310000 Earthwork
Page 220 Section 316216 Steel Pipe
Page 234 Section 355100 Floating Structures
Page 245 Attachment 1 State Environmental Policy Act (SEPA) - Determination of Non-Significance (DNS)
Page 287 Attachment 2 San Juan County Shoreline Substantial Development Permit
Page 309 Attachment 3 Marine Mammal Monitoring Plan
Page 317 Attachment 4 Marbled Murrelet Monitoring Plan
Page 336 Attachment 5 Washington Department of Fish & Wildlife - Hydraulic Project Approval (HPA)
Page 343 Attachment 6 Washington Department of Natural Resources - Aquatic Lands Right of Entry
Page 365 Attachment 7 U.S. Army Corps of Engineers Letter of Permission
Page 370 Attachment 7a U.S. Army Corps of Engineers - Project Notification Summary Sheet
Page 376 Attachment 7b U.S. Army Corps of Engineers - General Construction Measures & Essential Fish Habitat Conservation Measures
Page 391 Attachment 7c U.S. Army Corps of Engineers - Project Design Criteria #5
Page 396 Attachment 7d U.S. Army Corps of Engineers - Project Design Criteria #6
Page 399 Attachment 7e U.S. Army Corps of Engineers - Letter of Permission General Conditions
Page 405 Attachment 7f U.S. Army Corps of Engineers - Certificate of Completion
Page 407 Attachment 7g Grette Associates, LLC Reid Harbor Moorage Replacement Biological Evaluation & Essential Fish Habitat Assessment - ASACE Letter of Permission
Page 482 Attachment 7h Grette Associates, LLC Reid Harbor Moorage Replacement Eelgrass & Macroalgae Verification Survey - USACE Letter of Permission
Page 485 Attachment 8 Inadvertent Discovery Plan
Page 496 Attachment 9 State Environmental Policy Act (SEPA) - Determination of Non-Significance (DNS) (Alternate Bid Item A1)
Page 522 Attachment 10 San Juan County- Shoreline Substantial Development Permit Landuse-22-0019 (Alternate Bid Item A1)
Page 540 Attachment 11 Marine Mammal Monitoring Plan March 2022 (Alternate Bid Item A1)
Page 547 Attachment 12 Marbled Murrelet Monitoring Plan March 2022 (Alternate Bid Item A1)
Page 566 Attachment 13 Washington Department of Fish & Wildlife - Hydraulic Project Approval (HPA) (Alternate Bid Item A1)
Page 572 Attachment 14 Washington Department of Natural Resources - Aquatic Land Lease No. 20-105889 (Alternate Bid Item A1)
Page 619 Attachment 15 U.S. Army Corps of Engineers Letter of Permission (Alternate Bid Item A1)
Page 624 Attachment 15a U.S. Army Corps of Engineers - Project Notification Summary Sheet (Alternate Bid Item A1)
Page 630 Attachment 15b U.S. Army Corps of Engineers - General General Construction Measures & Essential Fish Habitat Conservation Measures (Alternate Bid Item A1)
Page 645 Attachment 15c U.S. Army Corps of Engineers - Project Design Criteria #5 (Alternate Bid Item A1)
Page 650 Attachment 15d U.S. Army Corps of Engineers - Habitat Improvement Plan (Alternate Bid Item A1)
Page 657 Attachment 15e U.S. Army Corps of Engineers - Letter of Permission General Conditions (Alternate Bid Item A1)
Page 663 Attachment 15f U.S. Army Corps of Engineers - Certificate of Completion (Alternate Bid Item A1)
Page 665 Attachment 15g Greete Associates, LLC - Sucia Island Floating Pumpout Station Installation - Biological Evaluation & Essential Fish Habitat Assessment - USACE Letter of Permission (Alternat
Page 726 Attachment 15h Grette Associates, LLC - Suica Island Floating Pumpout Station Installation - Eelgrass & Macroalgae Preliminary Survey - ASACE Letter of Permission (Alternate Bid Item A1)
Page 730 Attachment 16 Geotechnical Engineering Services Report - Stuart Island State Park Improvements (Base Bid)
Page 800 Attachment 17 Geotechnical Engineering Services Report - Suica Island State Park Improvements (Alternate Bid Item A1)