77th Street Court East and 205th Avenue Sewer Repairs, City of Bonney Lake, WA
$850,000 to $1,000,000
Low Bid:
| Bids Received: 16 | ||
| Apparent Low Bid | SCI | $ 598,844.55 |
| 2nd | Hoffman | $ 601,204.28 |
| 3rd | Strickland | $ 661,932.43 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Bonney Lake
Public Services Center
21719 96th Street E
Buckley WA, 98321
253-447-3270
https://www.cobl.us
Contacts:
Andrew Fonda, Assistant City Engineer
253-447-3270
fondaa@bonneylake.gov
Ken Gill, City Engineer
253-410-1494
gillk@bonneylake.gov
Issued by:
www.bxwa.com
Prebid: 10/29 @ 2:00 pm at 19437 77th Street Court E
Description:
The City of Bonney Lake is requesting bids from qualified contractors for the replacement of approximately 203 linear feet of 8" PVC sewer main on 77th Street Court East, reconnecting of side sewers, water service replacement and hot mix asphalt surface restoration; as well as repairs of a damaged 8" PVC sewer main on 205th Avenue by replacing approximately 14 linear feet of the sewer main and reconnecting a 6" sewer side service.