Cloney Park Storm Pipe Replacement, City of Longview, WA
Low Bid:
Bids Received: 5 | ||
Apparent Low Bid | Swofford Excavating | $ 1,288,665.51 |
2nd | Advanced Excavating Specialist | $ 1,596,630.51 |
3rd | NW Construction | $ 1,630,188.54 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Longview
1525 Broadway
Longview, WA 98632
360-442-5200
Fax: 360-442-5953
Contact:
Ivona Kininmonth, Project Engineer
360-442-5208
ivonak@ci.longview.wa.us
Issued by:
www.bxwa.com
Notes:
Engineer's Estimate: $1,200,000
Bid Opening Information:
https://us02web.zoom.us/j/84821994372
+12532050468,,84821994372# US or +12532158782,,84821994372# US (Tacoma)
Webinar ID: 848 2199 4372
Description:
The project includes abandonment of 1925 LF of existing 54" storm pipe with cdf, installation of 790 LF of 30" pipe, 1075 LF of 12" pipe, storm water manholes and catch basin structures, associated concrete / asphalt pavement restoration, dewatering, traffic control, and any other incidental work necessary to complete the specification work in accordance with the contract plans, contract provisions and the standard specifications.