2026 Phase 1 Water Main Replacement, City of Bellevue, WA #25085
$4,400,000 to $5,400,000
Low Bid:
| Bids Received: 7 | ||
| Apparent Low Bid | D&G Backhoe, Inc. | $ 3,595,137.61 |
| 2nd | Kar-Vel Construction | $ 3,606,136.07 |
| 3rd | Fury Site Works, Inc. | $ 3,662,594.50 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Bellevue
Contracting Services Division
450 - 110th Avenue NE
Bellevue, WA 98004
425-452-4870
bellevuewa.gov
Contact:
Jim Stockwell, Project Engineer
425-452-4868
jstockwell@bellevuewa.gov
Issued by:
www.bxwa.com
Notes:
Bid Opening Information:
Join Microsoft Teams Meeting
https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting
Meeting ID: 240 560 793 866 0
Passcode: XD3446Fh
Or call in (audio only)
+1 206-452-7011,,258315036# United States, Seattle
Phone Conference ID: 258 315 036#
Description:
Work contemplated to be performed under this contract is as follows:
• Constructing approximately 7,100 LF of ductile iron water mains,
• Installing new fire hydrant assemblies,
• Installing replacement water services,
• Construction dewatering,
• Relocating existing utilities (as required),
• Abandoning asbestos cement pipe,
• Restoring surface conditions, including asphalt trench patching and concrete curbs, gutters, and sidewalks,
• Performing traffic control,
• Other work as required to complete the project