Vasa Creek / SE Newport Way Culvert Repairs and Outlet Dissipation, City of Bellevue, WA #24020
$650,000 to $750,000
Low Bid:
Bids Received: 4 | ||
Apparent Low Bid | Ecogrind Site Solutions LLC | $ 495,026.12 |
2nd | Apcon Tech Inc. | $ 539,888.56 |
3rd | Road Construction Northwest, Inc. | $ 613,125.98 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Bellevue
Contracting Services Division
450 - 110th Avenue NE
Bellevue, WA 98004
425-452-4870
bellevuewa.gov
Contact: Jay Hummel
425-452-4160
jhummel@bellevuewa.gov
Issued by:
www.bxwa.com
Description:
Work contemplated to be performed under this contract is as follows:
- Sewer manhole activities to include channelizing sump with concrete.
- Stream bed activities to include stream bypass, removal of existing gabion mattresses, excavation and grading of stream channel, placement of various sized boulders, placement of large woody material, and placement of streambed sediment, cobbles, and boulders
- Landscape restoration.
- Traffic control and TESC to support the above activities.