City of Vancouver - Public Works Operations Campus: Bid Group 3, Vancouver, WA - Bid Package 23A - Geo-Exchange    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 510 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 2 Content Index
Page 3 Section 00020 Instructions to Bidders
Page 9 Bid Form
Page 12 Exhibit A Scope of Work / Supply & Clarifications / Qualifications
Page 14 Exhibit B Drawings & Sketches, Specifications, Addenda & Other Documents
Page 18 Exhibit C Alternates, Unit Prices & Labor Rates
Page 23 Exhibit E Standard Subcontract Terms & Conditions
Page 42 Exhibit F Supplier Code of Conduct
Page 47 Exhibit G Standard Insurance Requirements
Page 58 Exhibit H Interim Estimate for Payment, Waiver & Release
Page 60 Exhibit I Final Estimate for Payment, Unconditional Waiver & Release
Page 63 Exhibit J Standard Subcontractor Environmental Health & Safety Requirements
Page 67 Exhibit K Standard Change Order
Page 69 Exhibit M Project Specific Requirements
Page 82 Exhibit N Supplemental Terms & Conditions to Subcontract for Use in the State of Washington
Page 90 Exhibit O Performance Bond
Page 92 Payment Bond
Page 94 Exhibit PS-1 Owner / Contractor Agreement
Page 95 AIA Document A133-2019 Standard Form of Agreement Between Owner & Contractor as Constructor
Page 127 AIA Document A201-2017 General Conditions of the Contract for Construction
Page 191 Exhibit 2 Cost Responsibility Matrix
Page 206 Exhibit PS-2 Environmental Health & Safety Plan Updates
Page 207 Exhibit R Project Specific Quality Management
Page 211 Exhibit S Authorized Signatories
Page 212 Exhibit T1 Supplier Diversity Program Summary
Page 214 Exhibit T2 Instructions to Bidders
Page 215 Exhibit T-3 Diverse Business Status Verification
Page 218 Exhibit U Sub-Subcontractor Identification
Page 220 Exhibit X Site Requirements & Logistics
Page 225 Exhibit X-1 Vancouver Public Operations Center - Early Work Site Logistics Plan
Page 226 Exhibit X-2 Environmental, Health & Safety Manual