Printable Drawing List

Sumner High School Addition Phase 2, Sumner, WA - Early Bid Set Plans Volume 3

G0.00v3 Cover Sheet & Project Team
G0.01v3 Drawing Index & Symbol Legend
M0.01 Mechanical Legend
M0.02 Mechanical Abbreviations & General Notes
M0.03 Mechanical Schedules
M0.04 Mechanical Schedules
M0.05 Mechanical Schedules
M0.06 Mechanical Schedules
M0.07 Mechanical Schedules
M0.08 Energy Code Notes & Schedules
M0.09 Energy Code Schedules
M0.10 Energy Code Schedules
M1.00 Mechanical Site Plan
MD5.01 Enlarged Equipment Room Demolition Plan
MD8.01 Heating Water Riser Demolition Diagram
MD8.02 Chilled Water Riser Demolition Diagram
M1.11 Foundation Plan - Area A
M1.12 Foundation Plan - Area B
M1.13 Foundation Plan - Greenhouse & Animal Science
M2.11 First Floor Plumbing Plan - Area A
M2.12 First Floor Plumbing Plan - Area B
M2.13 First Floor Plumbing Plan - Greenhouse & Animal Science
M2.21 Second Floor Plumbing Plan - Area A
M2.22 Second Floor Plumbing Plan - Area B
M2.31 Third Floor Plumbing Plan - Area A
M2.32 Third Floor Plumbing Plan - Area B
M2.41 Mechanical Equipment Penthouse Plumbing Plan - Area A
M2.42 Mechanical Equipment Penthouse Plumbing Plan - Area B
M3.11 First Floor HVAC Plan - Area A
M3.12 First Floor HVAC Plan - Area B
M3.21 Second Floor HVAC Plan - Area A
M3.22 Second Floor HVAC Plan - Area B
M3.31 Third Floor HVAC Plan - Area A
M3.32 Third Floor HVAC Plan - Area B
M3.41 Mechanical Penthouse HVAC Plan - Area A
M3.42 Mechanical Penthouse HVAC Plan - Area B
M4.11 First Floor HVAC Piping Plan - Area A
M4.12 First Floor HVAC Piping Plan - Area B
M4.21 Second Floor HVAC Piping Plan - Area A
M4.22 Second Floor HVAC Piping Plan - Area B
M4.31 Third Floor HVAC Piping Plan - Area A
M4.32 Third Floor HVAC Piping Plan - Area B
M4.41 Mechanical Equipment Penthouse HVAC Piping Plan - Area A
M4.42 Mechanical Equipment Penthouse HVAC Piping Plan - Area B
M5.01 Enlarged Equipment Room Plan
M5.02 Chiller Plan
M5.03 Enlarged Boiler Room Flue Plans
M5.04 Enlarged Culinary Plumbing Plan
M6.00 Overall Mechanical Roof Plan
M7.01 Overall First Floor Fire Sprinkler Plan
M7.02 Overall Second Floor Fire Sprinkler Plan
M7.03 Overall Third Floor Fire Sprinkler Plan
M7.04 Overall Mechanical Equipment Penthouse Fire Sprinkler Plan
M8.01 Heating Water Riser Diagram
M8.02 Chilled Water Riser
M8.03 Natural Gas Riser Diagram
M9.01 Mechanical Details
M9.02 Mechanical Details
M9.03 Mechanical Details
M9.04 Mechanical Details
M9.05 Mechanical Details
M9.06 Mechanical Details
E0.01 Electrical Legend & Drawing Index
E0.02 Electrical Abbreviations & General Notes
E0.03 Telecom & Low-Voltage Rough-In Schedules
E0.04 Light Fixture Schedule
E0.05 Mechanical Equipment Schedule
E0.10 Access Control Schedules
E0.11 Security Camera Schedule
ED1.01 Electric Demolition Site Plan
E1.01 Electrical Site Plan
E1.02 Telecom Site Plan
E2.11 First Floor Lighting Plan - Area A
E2.11A First Floor Lighting Control Zone Plan - Area A
E2.12 First Floor Lighting Plan - Area B
E2.12A First Floor Lighting Control Zone Plan - Area B
E2.21 Second Floor Lighting Plan - Area A
E2.21A Second Floor Lighting Control Zone Plan - Area A
E2.22 Second Floor Lighting Plan - Area B
E2.22A Second Floor Lighting Control Zone Plan - Area B
E2.31 Third Floor Lighting Plan - Area A
E2.31A Third Floor Lighting Control Zone Plan - Area A
E2.32 Third Floor Lighting Plan - Area B
E2.32A Third Floor Lighting Control Zone Plan - Area B
E2.41 Mechanical Equipment Penthouse Lighting Plan - Area A
E2.41A Mechanical Equipment Penthouse Lighting Control Zone Plan - Area A
E2.42 Mechanical Equipment Penthouse Lighting Plan - Area B
E2.42A Mechanical Equipment Penthouse Lighting Control Zone Plan - Area B
E3.10 Overall First Floor Power Plan
E3.11 First Floor Power Plan - Area A
E3.12 First Floor Power Plan - Area B
E3.20 Overall Second Floor Power Plan
E3.21 Second Floor Power Plan - Area A
E3.22 Second Floor Power Plan - Area B
E3.30 Overall Third Floor Power Plan
E3.31 Third Floor Power Plan - Area A
E3.32 Third Floor Power Plan - Area B
E3.41 Mechanical Equipment Penthouse Power Plan - Area A
E3.42 Mechanical Equipment Penthouse Power Plan - Area B
E3.50 Overall Roof Power Plan
E3.50a Photovoltaic & Solar Readiness Plan
E5.11 First Floor Fire Alarm Plan - Area A
E5.12 First Floor Fire Alarm Plan - Area B
E5.21 Second Floor Fire Alarm Plan - Area A
E5.22 Second Floor Fire Alarm Plan - Area B
E5.31 Third Floor Fire Alarm Plan - Area A
E5.32 Third Floor Fire Alarm Plan - Area B
E5.41 Mechanical Equipment Penthouse Fire Alarm Plan - Area A
E5.42 Mechanical Equipment Penthouse Fire Alarm Plan - Area B
E6.11 First Floor Telecom Plan - Area A
E6.12 First Floor Telecom Plan - Area B
E6.21 Second Floor Telecom Plan - Area A
E6.22 Second Floor Telecom Plan - Area B
E6.31 Third Floor Telecom Plan - Area A
E6.32 Third Floor Telecom Plan - Area B
E6.41 Mechanical Equipment Penthouse Telecom Plan - Area A
E6.42 Mechanical Equipment Penthouse Telecom Plan - Area B
E7.01 Electrical Animal Science & Greenhouse Plans
E7.01a Electrical Animal Science & Greenhouse Plans
E7.02 Electrical Enlarged Culinary Arts Plan
E7.03 Enlarged Electrical Aero-Space MFRG Plan
E7.04 Electrical Enlarged Plans
E7.05 Electrical Details
E7.06 Electrical Details
E7.07 Electrical Details
E8.01 Telecom & Low-Voltage Enlarged Plans & Details
E8.02 Telecom Details
E8.03 Classroom AV Details
E8.04 Access Control Details
E8.05 Security Camera Details
E8.06 Rescue Assistance System Details
E9.01 Electrical One-Line Diagram
E9.02 Telecom One-Line Diagrams
E10.01 Panel Schedules
E10.02 Panel Schedules
E10.03 Panel Schedules
E10.04 Panel Schedules
E10.05 Panel Schedules
FS1.10 First Floor Food Service Equipment / Plumbing / Electrical Plans
FS2.10 Second Floor Culinary Arts Equipment Plan
FS2.11 Second Floor Culinary Arts Plumbing Plan
FS2.12 Second Floor Culinary Arts Mechanical Plan
FS2.13 Second Floor Culinary Arts Electrical & Refrigeration Plan
FS3.10 Second Floor Culinary Arts Hood Details
FS3.11 Second Floor Culinary Arts Hood Details
FS3.12 Second Floor Culinary Arts Hood Details
FS3.13 Second Floor Culinary Arts Hood Details
FS3.14 Second Floor Culinary Arts Hood Details
FS3.15 Second Floor Culinary Arts Hood Details
FS3.16 Second Floor Culinary Arts Hood Details
FS3.17 Second Floor Culinary Arts Hood Details
FS4.10 First & Second Floor Walk-In Details
FS4.11 Second Floor Culinary Arts Refrigeration Details
FS4.12 First Floor Agricultural Science Refrigeration Details
FS5.10 Food Service Elevation & Fabrication Details
FS5.11 Food Service Elevation & Fabrication Details
FS5.12 Food Service Elevation & Fabrication Details
FS5.13 Food Service Elevation & Fabrication Details