Mariner High School Renovation & Addition - Multiple Bid Packages, Mukilteo School District, Everett, WA - Specs Volume 1    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 546 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 2 Division 00 Procurement and Contracting Requirements
Page 3 Section 000110 Table of Contents
Page 9 Section 001116 Invitation to Bidders
Page 12 Section 002113 Instructions to Bidders
Page 19 Section 002205 GC/CM Process
Page 32 Section 002217 Safety
Page 34 Section 002410 General Scope of Work
Page 44 Construction Site Plans
Page 47 Section 002413 Specific Scope of Work by Bid Package
Page 73 Attachment: Bid Package Matrix
Page 77 Section 003100 Available Project Information
Page 79 Limited Hazardous Building Materials Assessment Report
Page 262 Section 003113 Schedule
Page 263 Attachment: Summary Schedule
Page 264 Section 004113 Bid Form
Page 267 Section 004322 Schedule of Unit Prices
Page 268 Section 005213 Form of Contract
Page 269 Subcontract Performance Bond
Page 272 Subcontractor Payment Bond
Page 274 Standard Subcontract
Page 292 Section 007200 General Conditions
Page 293 General Conditions of the Contract for Construction (For GC/CM Projects)
Page 363 Section 007343 Wage Rate Requirements
Page 365 Division 01 General Requirements
Page 366 Section 011000 Summary
Page 372 Section 011110 Summary of Hazardous Materials
Page 379 Section 012000 Price and Payment Procedures
Page 383 Section 012300 Alternates
Page 385 Section 012500 Substitution Procedures
Page 389 Section 012500A Substitution Request Form
Page 390 Section 012600 Contract Modification Procedures
Page 396 Section 013100 Project Management and Coordination
Page 406 Section 013115 Communication
Page 412 Section 013119 Project Meetings
Page 420 Section 013216 Construction Progress Schedule
Page 430 Section 013300 Submittal Procedures
Page 442 Section 013300A Consent for the Release of Electronic Media
Page 443 Section 013546 Indoor Air Quality Procedures
Page 449 Section 014000 Quality Requirements
Page 459 Section 014100 Air Barrier Testing Procedures
Page 465 Section 015000 Temporary Facilities & Controls
Page 477 Section 015639 Tree Protection
Page 490 Tree Protection Area
Page 491 Section 015713 Temporary Erosion and Sediment Control
Page 500 Section 016000 Product Requirements
Page 504 Section 017000 Execution
Page 512 Section 017419 Construction Waste Management and Disposal
Page 518 Section 017700 Closeout Procedures
Page 528 Section 018113 Sustainable Design Requirements
Page 532 Section 019113 General Commissioning Requirements