Project #CRN223          Bid Date: 12/8/2026 @ 2:00 pm PST

Madison Elementary School Replacement, Everett School District, Everett, WA #13:26/27

$51,900,000

Plans Volume 1
Plans Volume 2
Specs Volume 1
Specs Volume 2
Specs Volume 3
Appendix

Request notification by email when new documents are added to this project.

Builders Exchange of Washington, Inc. Subs and Suppliers

Bids to:
Cornerstone General Contractors, Inc
11805 North Creek Parkway S, Suite 115
Bothell, WA 98011
425-481-7460
Fax: 425-481-7497

Contact: Dan Lampert
danl@cornerstonegci.com

Description:
The scope of work includes:
Phase 1 - Perform utility reroute and construct new school that includes the south portion of the parking lot.
Phase 2 - Perform demolition and abatement, construct sports field, storm pond and parking lot construction.

Refer to spec section 005200 -Phasing for phasing schedule.
Phase 1: 03/29/2027 - 06/16/2028
Phase 2: 06/20/2028 - 06/29/2029