Madison Elementary School Replacement, Everett School District, Everett, WA #13:26/27
$51,900,000
Plans Volume 1
Plans Volume 2
Specs Volume 1
Specs Volume 2
Specs Volume 3
Appendix
Request notification by email when new documents are added to this project.
Builders Exchange of Washington, Inc. Subs and Suppliers
Bids to:
Cornerstone General Contractors, Inc
11805 North Creek Parkway S, Suite 115
Bothell, WA 98011
425-481-7460
Fax: 425-481-7497
Contact: Dan Lampert
danl@cornerstonegci.com
Description:
The scope of work includes:
Phase 1 - Perform utility reroute and construct new school that includes the south portion of the parking lot.
Phase 2 - Perform demolition and abatement, construct sports field, storm pond and parking lot construction.
Refer to spec section 005200 -Phasing for phasing schedule.
Phase 1: 03/29/2027 - 06/16/2028
Phase 2: 06/20/2028 - 06/29/2029